大货季排产实录:4万日产能是怎么保证交期的 - 上海友孚包装制品有限公司<!-- Article + 真实作者 Person schema(GEO 实体:2026-10-10) --> <script type="application/ld+json"> {"@context":"https://schema.org","@type":"Article","headline":"大货季排产实录:4万日产能是怎么保证交期的","datePublished":"2026-10-01","dateModified":"2026-10-01","author":{"@type":"Person","name":"Jimmy","alternateName":"王磊","jobTitle":"Founder, Yoofo Packaging","description":"Founder of Shanghai Yoofo Packaging Products Co., Ltd., with 30 years of experience in packaging manufacturing.","worksFor":{"@type":"Organization","name":"Shanghai Yoofo Packaging Products Co., Ltd.","url":"https://customgiftboxesfactory.com/"},"sameAs":["https://www.instagram.com/yoofo.packaging","https://www.facebook.com/1303035282901554"]},"publisher":{"@type":"Organization","name":"Shanghai Yoofo Packaging Products Co., Ltd.","alternateName":"Yoofo Packaging","url":"https://customgiftboxesfactory.com/","logo":{"@type":"ImageObject","url":"https://customgiftboxesfactory.com/uploads/logo-packaging.png"}},"mainEntityOfPage":{"@type":"WebPage","@id":"https://customgiftboxesfactory.com/zh/article/peak-season-production-scheduling"}}</script>
+86-15906266503 [email protected] 上海市青浦区白鹤镇鹤吉路99号西楼
banner
动态
当前位置 首页 › 新闻博客 > 大货季排产实录:4万日产能是怎么保证交期的

大货季排产实录:4万日产能是怎么保证交期的

作者 Jimmy 发布: 2026-10-01

每年中秋、春节前两个月,是礼盒厂最难熬的时候:订单全挤在一起,谁都说自己急。4万的日产能不是喊出来的,是靠排产排出来的。我们的排产逻辑公开一下:

第一,印刷机分工。海德堡9+1和9+2两台机,一台跑常规四色,一台跑多色+特殊工艺,互不抢机台。瓶颈工序永远先排。

第二,工序前置。刀模、烫金版这些要外协的东西,订单一下就同步下单,不等印刷完才想起来。面纸印好直接进后道,不在仓库过夜。

第三,质检分三段。印刷首件签样、后道首件签样、成型全检。问题发现得越早,返工成本越低,交期越不受影响。

第四,留余量。排产永远按85%的产能排,剩下15%应对插单和返工。把产能排满的工厂,第一个延期的一定是它。

交期这件事,拼的不是机器多快,是计划做得多细。如果你有大货季的订单,建议提前3-4周下单,把打样和备料的时间留足。